CRITICAL FACTORS INFLUENCING IMPLEMENTATION OF ROAD PROJECTS IN KENYA

Authors

  • Nelly Jebitok Jomo Kenyatta University of Agriculture and Technology
  • DR. Joyce Nzulwa Jomo Kenyatta University of Agriculture and Technology

DOI:

https://doi.org/10.47941/jepm.302

Keywords:

Project financial resources, project management contract, project requirements, implementation of road projects

Abstract

Purpose: The Purpose of the study was to establish Critical factors influencing implementation of road projects.

Methodology: The study adopted a descriptive survey design. The target population of the study was all the road engineers, middle managers in department of KRB. The sample size was 188 respondents. Data collected was cleaned, pretested, validated, and coded, summarized and analyzed using statistical package of SPSS V23.  The study findings were presented using graphs, histograms, bar charts and pie charts.  Conclusions were derived based on the P.value and the coefficient of determination. 

Results: The study found that the key significant determinants of sustainability of water projects in Machakos County were capacity of the project management, government policies, monitoring and resource support. The study concluded that project management capacity had the greatest determinant ofsustainabilityofwater projects in Machakos County, followed by resource support, then monitoring while government policy had the least determinant of sustainability of water projects in Machakos County.

Contribution to policy and practice: The study recommends that the government should advocate for proper planning with involvement of the benefiting community and timely implementation with the required results. This can be done through making of a policy by the ministry demanding for the practice of the same by the involved organizations. The project committee should set up financial structures considering both rising of funds and dissemination of the same in relation to operating and maintaining of the project. This can be done through learning and training on the same. The study also recommended that water beneficiaries and management should be sensitized to improve their knowledge on conservation and protection of water facilities.

Downloads

Download data is not yet available.

Author Biographies

Nelly Jebitok, Jomo Kenyatta University of Agriculture and Technology

Post graduate student.

DR. Joyce Nzulwa, Jomo Kenyatta University of Agriculture and Technology

Lecturer

References

Al-Meshekeh, H.S., Langford, D.A. (2009), "Conflict management and construction project effectiveness: a review of the literature and development of a theoretical framework", Journal of Construction Procurement, Vol. 5 No.1, pp.58-75.

Al-Momani H., (2010), Examining service quality within construction processes, Technovation, 20, 643.651

Andersen, E.S., Grude, K.V., and Hang, T. (2010).Goal Directed Project Management: Effective techniques and strategies (Trans. From Norwegian by Roberta Wiig), 2nd edition. London: Kogan Page.

Baiden, B.K., (2007). Framework of the Integration of the Project Delivery Team.Unpublished Ph.D. Thesis, Southborough University.

Belbin, R.M. (2004), Management Teams – Why They Succeed or Fail, 2nd ed., Elsevier Butterworth-Heinemann, Amsterdam

Chan, A.P.C. (2006), Determinants of project success in the construction industry of Hong Kong, University of South Australia, Armidale,

Chan, A.P.C. (2006a), "Novation contract – Client's roles across the project life cycle", Proceedings of CIB W92 Procurement Systems North Meets South: Developing Ideas, 14-17 January 2006, South Africa, pp.31-9.

Chan, A.P.C., Chan, D.W.M. (2003), "A benchmark model for construction duration in publichousing developments", International Journal of Construction Management, Vol. 3 No.1, pp.11-14

Cheng, J., Proverbs, D.G., Oduoza, C.F., (2011). The satisfaction levels of UK constructionClients based on the performance of consultants. Engineering, Construction Architectural Management 13 (6), 567–583. 42

Chervier, S. (2003). Cross-cultural management in multinational project groups, Journal ofWorld Business 38, 141–149.

Deakin, P. (2009), "Client's local experience on design and build projects", Seminar Proceedings on Design and Build Procurement System, January, Hong Kong, pp.11-16

Ellis, R D & Thomas, H R (2003). The root causes of delays in highway construction. Final report.Transportation Research Board, Washington, D.C.

Ely, R.J., Thomas, D.A.,( 2001). Cultural diversity at work: the effects of diversity perspectives on work group processes and outcomes. Administrative Science Quarterly 46 (2), 229–273.

Granath, J.Å., Hinnerson, J. (2002), Delphi Study, Facility Management, School of Architecture, Chalmers University of Technology, Gothenburg

Hauschildt, J., Keim, G., Medcof, J.W. (2000), "Realistic criteria for project manager selection and development", Project Management Journal, Vol. 31 No.3, pp.23-32.

Haynes, N. & Love, P. E. D. (2004). Psychological Adjustment and Coping among ConstructionProject Managers.Construction Management and Economics, 22, 129-140.

Heaney, C. A., Price, R. H. & Rafferty, J. (2010).Increasing Coping Resources at Work: a Field Experiment to Increase Social Support, Improve Work Team Functioning, and Enhance Employee Mental Health.Journal of Organizational Behaviour, 16, 335-352.

Hemlin, D. (2009), "Contractor's local experience on design & build projects", Seminar Proceedings on Design and Build Procurement System, January, Hong Kong, pp.17-26 43

Hidenori, K. (2010), "Trust, integration and leadership: tenets of Japanese design and build", Design and Build Projects – International Experiences International Congress on Construction, 5-6 October, Singapore, pp.15-25.

Hussin A. &Abdelnasor O. (2006) “Role of Professionals in Construction Industry” The

International Conference on Administration and Business, 14-15 November, Romania, p248

Kenya Roads Board project publications (2009-2012)

Kok, S.H. (2010), "Design and build – the local experience (with Public Client)", Design and Build Projects – International Experiences International Congress on Construction, 5-6 October, Singapore, pp.223-645.

Kothari, C. R. (2004). Research methodology: Methods and techniques, 2Ed. New Delhi: Wiley.

Lamont, A.H. (2009), "Evaluation of design & build tenders", Seminar Proceedings on Design and Build Procurement System, January, Hong Kong, pp.37-48

Lenard, H. & Francis, V. (2004).The Work-life Experiences of Office and Site-based Employees in the Australian construction industry.Construction Management and Economics, 22, 991-1002.

Leung, K.S. (2009), "Characteristics of design and build projects", Seminar Proceedings on Design and Build Procurement System, January, Hong Kong, pp.1-10.

Lewis, J. (2007). Mastering project management: Applying advanced concepts to systems thinking, control & evaluation, resource allocation. McGraw Hill Professional.

Mbeche I., (2000). Project Planning, Implementation and Evaluation-A Training Manual,

Ng, S. T., Skitmore, R. M. & Leung, T. K. C. (2005).Manageability of Stress among Construction Project Participants. Engineering, Construction and Architectural Management, 12 (3), 264-282.

Ochieng, E.G., (2008).Framework for Managing Multicultural Project Teams.Unpublished Ph.D. Thesis.Loughborough University.

Pearson, J.C., Nelson, P.E., (2003). Human Communication. McGraw-Hill, New York.

Project management institute (2012), a guide to the project management body of knowledge.6th Ed. PA.Newton square Project management institute.

Rijk, A. E., Blanc, P. M., Schaufeli, W. B., &Jonge, J. J. (2008).Active Coping and Need for Control as Moderators of the Job Demand-control Model: Effects on Burnout. Journal of Occupational and Organizational Psychological, 71, 1-18.

Rowlinson, S. (2007), "Procurement systems: the view from Hong Kong", Procurement – a Key to Innovation: International Symposium of Commission W92, Montreal, pp.665-72.

Smith, A., Wilkins, B. (2006), "Team relationships and related critical factors in the successful procurement of health care facilities", Journal of Construction Procurement, Vol. 2 No.1, pp.30-40.

United Nation Centre for Regional Development.August, 2000 Nairobi, pp 31-39.

Weatherley, S., (2011). ECI in Partnership with Engineering Construction Industry Training Board (ECITB), ECI UK Master class Multicultural Project Team Working, London, 6th December, .

Yip, B., Rowlinson, S., Kvan, T. &Lingard, H. (2005). Job Burnout within the Hong Kong Construction Industry: A Cultural Perspective. Proceedings of the CIB

Published

2019-05-22

How to Cite

Jebitok, N., & Nzulwa, D. J. (2019). CRITICAL FACTORS INFLUENCING IMPLEMENTATION OF ROAD PROJECTS IN KENYA. Journal of Entrepreneurship and Project Management, 4(2), 1–22. https://doi.org/10.47941/jepm.302

Issue

Section

Articles