Project Stakeholder Management and Performance of World Bank Funded Projects in Nairobi City County, Kenya

Authors

  • Abdi Dima Wario Jomo Kenyatta University of Agriculture and Technology
  • Dr. Noor Ismail Shale-Phd Jomo Kenyatta University of Agriculture and Technology

DOI:

https://doi.org/10.47941/jepm.3849

Keywords:

Project Stakeholder Management, Stakeholder Engagement, Continuous Monitoring and Adjustment

Abstract

Purpose: This study sought to examine the influence of stakeholder management practices on the performance of World Bank funded projects in Nairobi City County, Kenya. Specifically, the study investigated the effect of stakeholder engagement and continuous monitoring and adjustment on project performance. The study was guided by Social Exchange Theory and Systems Theory.

Methodology: The study adopted a descriptive research design to examine the relationship between stakeholder management practices and project performance. The unit of analysis consisted of 40 World Bank funded projects implemented in Kenya between 2020 and 2025 with national implementation scope that includes Nairobi City County. A census approach was used at the project level, while purposive sampling was used to select four key respondents from each project, yielding an expected sample size of 160 respondents. Primary data was collected using a structured questionnaire containing closed-ended Likert scale items measuring stakeholder management practices and project performance. A pilot study involving approximately 10 percent of the target respondents was conducted to test the clarity and suitability of the instrument. Data was coded and analyzed using Statistical Package for Social Sciences (SPSS) version 29. Descriptive statistics including frequencies, percentages, means, and standard deviations summarized the data, while Pearson correlation analysis examined relationships between variables. Multiple regression analysis was used to determine the influence of independent variables on the performance of World Bank funded projects.

Findings: The study established that stakeholder engagement and continuous monitoring and adjustment were widely practiced in World Bank-funded projects in Nairobi City County. The findings further revealed that all the stakeholder management practices had a positive and significant influence on project performance, with continuous monitoring and adjustment emerging as the most influential factor. The study concluded that effective stakeholder management is essential for enhancing the performance and success of World Bank-funded projects.

Unique Contributions to Theory, Policy, and Practice: The study recommends strengthening stakeholder identification, engagement, expectation management, and continuous monitoring practices to improve project performance and sustainability.

Downloads

Download data is not yet available.

Author Biographies

Abdi Dima Wario, Jomo Kenyatta University of Agriculture and Technology

Masters Student

Dr. Noor Ismail Shale-Phd, Jomo Kenyatta University of Agriculture and Technology

Lecturer

References

Aaltonen, K., & Kujala, J. (2023). Stakeholder dynamics in project management: Toward a deeper understanding of stakeholder relationships in complex projects. International Journal of Project Management, 41(1), 1–14. https://doi.org/10.1016/j.ijproman.2022.10.002

Agyekum-Mensah, G., Knight, A., & Coffey, C. (2021). Stakeholder engagement and project success in developing countries. International Journal of Project Management, 39(4), 347–361. https://doi.org/10.1016/j.ijproman.2020.12.003

Bertalanffy, L. von. (1968). General system theory: Foundations, development, applications. George Braziller.

Bhattacherjee, A. (2001). Understanding information systems continuance: An expectation–confirmation model. MIS Quarterly, 25(3), 351–370. https://doi.org/10.2307/3250921

Etikan, I., & Bala, K. (2017). Sampling and sampling methods. Biometrics & Biostatistics International Journal, 5(6), 00149. https://doi.org/10.15406/bbij.2017.05.00149

Field, A. (2018). Discovering statistics using IBM SPSS statistics (5th ed.). SAGE Publications.

Flyvbjerg, B. (2021). Survival of the unfittest: Why the worst infrastructure gets built and what we can do about it. Oxford Review of Economic Policy, 37(2), 221–247. https://doi.org/10.1093/oxrep/grab003

Freeman, R. E. (1984). Strategic management: A stakeholder approach. Pitman.

Ika, L. A. (2021). Project success as a topic in international development. International Journal of Project Management, 39(2), 145–160. https://doi.org/10.1016/j.ijproman.2020.12.004

Ika, L. A., Diallo, A., & Thuillier, D. (2020). Project management in the international development industry. International Journal of Project Management, 38(7), 485–499. https://doi.org/10.1016/j.ijproman.2020.05.002

Kothari, C. R. (2004). Research methodology: Methods and techniques (2nd ed.). New Age International.

Kumar, R. (2019). Research methodology: A step-by-step guide for beginners (5th ed.). SAGE Publications.

Li, Y., Lu, Y., & Cui, Q. (2022). Understanding stakeholder management in megaprojects: A dynamic perspective. Project Management Journal, 53(3), 275–290. https://doi.org/10.1177/87569728221083455

Müller, R., Drouin, N., & Sankaran, S. (2020). Organizational project management as a source of competitive advantage. International Journal of Project Management, 38(4), 196–210. https://doi.org/10.1016/j.ijproman.2020.03.001

Nguyen, L. D., Mohamed, S., & Panuwatwanich, K. (2021). Stakeholder management and infrastructure project success in developing countries. Engineering, Construction and Architectural Management, 28(5), 1365–1383. https://doi.org/10.1108/ECAM-10-2019-0564

Oppong, G. D., Chan, A. P. C., & Dansoh, A. (2021). A review of stakeholder management performance attributes in construction projects. International Journal of Project Management, 39(4), 347–361. https://doi.org/10.1016/j.ijproman.2020.12.003

Pallant, J. (2020). SPSS survival manual (7th ed.). McGraw-Hill Education.

Prebanić, K. (2023). Stakeholder engagement in infrastructure projects and its influence on project success. Buildings, 13(7), 1785. https://doi.org/10.3390/buildings13071785

Thabane, L., Ma, J., Chu, R., Cheng, J., Ismaila, A., Rios, L., Robson, R., Thabane, M., Giangregorio, L., & Goldsmith, C. H. (2010). A tutorial on pilot studies: The what, why and how. BMC Medical Research Methodology, 10, 1. https://doi.org/10.1186/1471-2288-10-1

World Bank. (2024). Implementation status and results report: Second Kenya Informal Settlements Improvement Project (P167814). World Bank Group.