Influence of Procurement Specification Development on Performance of The Energy Sector in Kenya
DOI:
https://doi.org/10.47941/ijscl.463Keywords:
Procurement Specification Development, Stakeholder Involvement, Vetting and Approvals and Revision and StorageAbstract
Purpose: The purpose of the study was to assess the influence of procurement specifications development on performance of the energy sector in Kenya with an aim of making recommendations on proper use of procurement specification development practices among energy sector in Kenya.
Methodology: This research study adopted a descriptive research design approach. The researcher preferred this method because it allows an in-depth study of the subject. The target population was procurement officers in the energy sector in Kenya. The study employed stratified random sampling technique in coming up with a sample size of 154 respondents from a total of 253 target population in the energy sector in Kenya. The study combined two methods in its data collection that is, questionnaires and key informant interviews. After data collection, quantitative data was coded using Statistical Package for Social Science (SPSS) version 20. Data was analyzed through descriptive statistical methods such as means, standard deviation, frequencies and percentage. Inferential analyses were used in relation to correlation analysis and regression analysis to test the relationship between the four explanatory variables and the explained variable.
Results and conclusion: The independent variables reported R value of 0.796 indicating that there was perfect relationship between dependent variable and independent variables. R-Square is a commonly used statistic to evaluate model fit. R2 is 1 minus the ratio of residual variability. The coefficient of determination also called the R2 was 0.634. R2 value of 0.634 means that 63.4% of the corresponding variation in performance of the energy sector in procurement specification development in the energy sector in Kenya can be explained or predicted by (planning and analysis, stakeholder involvement, vetting and approvals, revision and storage) which indicated that the model fitted the study data. The Findings of the Study Indicated That Planning and Analysis, Stakeholder Involvement, Vetting and Approvals and Revision and Storage Have A Positive Relationship with Performance of The Energy Sector.
Unique contribution to theory, policy and practice: The study recommended that companies in the energy sector should embrace drivers of procurement specification development and further researches should to be carried out in other institutions to find out if the same results can be obtained.
Downloads
References
Ackerberg, D., & Botticini, M. (2012). Endogenous matching and the empirical determinants of contract form. International Journal of Political Economics, 110(3), 100-118
Agaba, E., & Shipman, N. (2014). Stakeholder Procurement Reform in Developing Countries: The Ugandan Experience. Thai (Eds.), Boca Raton, FL: Pr Academics Press. 8(4), 373-391.
Akech, J.M. (2010). Development partners and governance of stakeholder procurement in Kenya: enhancing democracy in the administration of aid. Int. law Politics.
Armstrong, M., & Baron, A. (2014). Managing performance: performance management in action. London: Chartered Institute of Personnel and Development.
Balogun, M.J. (2008). Performance Management and Agency Governance for Africa Development: The search for common cause on Excellence in the Stakeholder Service. UNCEA, Addis Ababa.
Bask, A.H. (2011). Relationships among TPL providers and members of supply chains- a strategic perspective. The Journal of Business and Industrial Marketing, 16(6), 470-486.
Bauknight, D., & Miller, R. J., (2015). Re-engineering Global Supply Chain. International Journal of Physical Distribution &procurement specification development Management 30 (1), 13-34.
Bolumole, Y. (2011). The Supply Chain Role of Third-Partyprocurement specification development Providers. International Journal ofprocurement specification development Management, 12(2), 87-102.
Bourlakis, C., & Bourlakis, M. (2015). Information technology safeguards,procurement specification development asset specificity and fourth-partyprocurement specification development network creation in the food retail chain, The Journal of Business & Industrial Marketing, 20 (2), 88-99.
Bowersox, J., Closs, J., & Cooper, M. (2010). Supply Chainprocurement specification development Management (3rd Ed); Boston, Mass: McGraw-Hill.
Bumstead, J., & Cannons, K. (2012). From 4PL to managed supply-chain operations,procurement specification development & Transport Focus, 4(4), 18-24
Buyukozkan, G., Feyzioglu, O. & Ersoy, M. (2015). Evaluation of 4PL operating models: A decision making approach based on 2-additive integral, International Journal of Production Economics, 121 (5), 112-120.
CCG. (2010). National Development Fund Report Instructional Structures and Reforms. Nairobi: Centre for Corporate Governance.
Chang, W., Chiang, M., & Pai, Y. (2012). Cooperative Strategy in Supply Chain Networks. International Journal of Industrial Marketing Management 12 (1), 11-19.
Christopher, M., & Peck, H. (2014). "Building the Resilient Supply Chain". International Journal ofprocurement specification development Management, 15(2), 1-13.
CIPS (2005). An Introduction to Performance Measurement of the Procurement Profession. Retrieved July 17, 2017, from Chartered Institute of Purchasing and Supply
Cousins, P., & Speckman, R. (2013). Strategic supply and the management of inter- and intra-organizational relationships, Journal of Physical Distribution &procurement specification development Management, 9(1), 19-29
Dean, A.M., & Kiu, C. (2012). Performance monitoring and quality outcomes in contracted services, International Journal of Quality & Reliability Management, 19 (4), 396-413
Dooren, W. (2009). Performance measurement in the Flemish stakeholder sector; a supply and demand approach. (Unpublished PhD thesis) Catholic University, Leuven
Evenett, J., & Hoekman, M., (2014). International disciplines on government procurement: a review of economic analyses and their implications, Centre for Economic Policy Research (CEPR)
Gianakis, G. (2012). "The promise of private sectorperformance measurement: anodyne or placebo?" International Journal of Stakeholder Administration, 2(6), 34-64.
Greiling, D. (2010). Performance measurement: a remedy for increasing the efficiency of Stakeholder services. International Journal of Productivity and Performance Management 55(6), 448-465.
Haakansson, H., & Ford, D. (2012). How companies interact in business networks? Journal of Business Research, 55(1), 133-139
Harland, C.M. (2009). Supply Chain Management: Relationships, Chains and Networks. British Journal of management, 21(14), 457-473
Kaufmann, M. (2008). Six questions on the cost of corruption with World Bank Institute of Global Governance Director: Danniel Kaufmann in News, the World Bank, Washington
Kombo, D., & Tromp, D. (2011). Project and Thesis Writing, an introduction. Nairobi: Pauline Stakeholderations Africa.
Kothari, C.R. (2014). Research methodology: Methods and Techniques. 2 Ed, New Age International.
Kumar, R., & Markeset, T. (2007). Development of performance-based service strategies for the oil and gas industry: a case study, Journal of Business & Industrial Marketing, 22(4), 272-80
Larry, H. (2013). Advanced Statistics in Research: Reading, Understanding, and Writing Up Data Analysis Results. Publisher: Shadow Finch Media LLC (January 7, 2013).
Lazear, E.P. (2010). Performance pay and productivity. Amer. Econom. Rev. 90(5), 1346-1361.
Liker, J. K., and Choi, T.Y., (2014). Building deeper supplier relationships. Harvard Business Review. 82 (12), 104-113
Liu, C., & Lyons, A. (2011). An analysis of third-partyprocurement specification development performance and service provision. Transportation Research Part E:procurement specification development and Transportation Review 34(47), 547-570.
Liu, L., & Yao, J. (2013). Multi-objective optimization algorithm analysis on supply chain resources integration decision in 4PL, In IEEE International Conference on Automation andprocurement specification development , 7(8), 1852-1857
Ljungberg, D., & Gebresenbet, G. (2014). Mapping out the potential for coordinated goods distribution in city centres: The case of Uppsala International Journal of Transport Management 8(3), 161-172.
Malta, V., Schapper, R., Calvo-Gonzale, O., & Berroa, D. (2011). Old Rules, New realities: Are existing stakeholder procurement systems addressing current and future needs? Washington, D.C.: The World Bank.
Mohan, G. (2010). Participatory Development. In Desai, Vandana and Potter, Rob eds. The Arnold Companion to development studies. London, UK: Hodder.
Mukhopadhyay, S.K., & Setaputra R., (2016). "The Role as the Reverse Logistic Integrator", International Journal of Physical Distribution &procurement specification development Management, 36(9), 716-729
Murphy, P., & Poist, R. (2010). Third Partyprocurement specification development : Some user versus provider perspectives. Journal of Businessprocurement specification development , 21 (1), 121-34
Narayanan, V., & Raman, A. (2014). Aligning incentives in supply chains. Harvard Business Review, 82(11), 94-102.
Neuman, W.L. (2010). Social Research Methods: Qualitative and Quantitative Approaches (Fourth Edition ed.). Boston.
Downloads
Published
How to Cite
Issue
Section
License
Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution (CC-BY) 4.0 License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.