Influence of Time Management on Implementation of Road Construction Projects in Kilifi County, Kenya

Authors

  • Njebi Mark Mutugi University of Nairobi
  • Prof. Dorothy Ndunge Kyalo University of Nairobi

DOI:

https://doi.org/10.47941/jepm.497
Abstract views: 455
PDF downloads: 279

Keywords:

Road construction projects, time management, implementation, activity sequencing, resource estimation, activity control and institutional capacity

Abstract

Purpose: Major road construction projects across Kilifi County have experienced delays in delivery due to a majority of contractors, both local firms and government agencies, failing to adhere to agreed-upon completion dates.it is in the backdrop of these problems that influenced the researcher to establish the influence of time management on the implementation of road projects in Kilifi County. The main purpose of this study was to examine the influence of time management on the implementation’s road constructions projects in Kilifi County.

Methodology: The study adopted cross sectional research design and collect data using questionnaires from 120 engineers/project managers, supervisors/inspectors and technicians/foremen from 12 organizations including five construction companies involved in urban road construction projects in Kilifi County, five service providers whose utility facilities run along road construction corridors in Kilifi County, and two state corporations charged with the management of road construction in Kenya. Data was analysed using both descriptive and inferential statistics with the help of IBM SPSS Statistics. Descriptive analysis involved the use of frequencies, percentages, mean and standard deviation in order to summarize the results of the various study variables. Inferential analysis involved the application of Pearson correlation and regression analysis to determine the nature of relationship between time management and implementation of road projects in Kilifi County.

Results: The study found out that activity sequencing positively and significantly affects road constructions projects in Kilifi County (r = 0.688, P=0.000 < 0.01). The study further determined that a unit improvement in activity sequencing would lead significantly lead to improvement in road project implementation (β = 0.127, t = 2.037, P=0.044 <0.05). It was also determined that resource estimation positively and significantly affects implementation of road constructions projects in Kilifi County (r = 0.721, P = 0.002 < 0.01). the analysis also showed that a unit improvement in resource estimation would lead to a unit improvement in road project implementation (β = 0.218, t = 2.741, P = 0.005<0.05). The study also determined that activity control significantly and positively predicts implementation of road constructions projects in Kilifi County (r = 0.909, P= 0.000< 0.01). The regression analysis showed that a unit improvement in activity control would significantly lead to an improvement in implementation of road construction projects in the county (β = 0.173, t =3.045, P = 0.003<0.05). Finally, the study found out that institutional capacity affects road projects implementation (r = 0.558, P=0. .003 < 0.01). It was also determined that institutional capacity has moderating influence on the relationship between time management and road project implementation (β = 0.185, t = 4.302, P=0.000 < 0.05).

Unique contribution to theory, policy and practice: The study recommended that for effective time management during implementation of road construction projects, there should be stakeholder involvement as this will facilitate ideas and perspective. Stakeholder involvement in time management and planning, will better their correspondence, improve accuracy of information, increase credibility and acceptance findings and finally improve the quality road constructions projects in Kilifi County.

Downloads

Download data is not yet available.

Author Biographies

Njebi Mark Mutugi, University of Nairobi

Postgraduate Student: The University of Nairobi  

Prof. Dorothy Ndunge Kyalo, University of Nairobi

Lecturer, University of Nairobi 

References

Aeon, B., & Aguinis, H. (2017). It’s about time: New perspectives and insights on time management. Academy of management perspectives, 31(4), 309-330.

Bundi, L. (2011). Challenges in the Management of Procurement Services Within Kenya Rural Roads Authority. Nairobi: University of Nairobi.

Ceniga, P., & Šukalová, V. (2015). Application of the Theory of Constraints in Supply Chain. In Applied Mechanics and Materials (Vol. 708, pp. 13-19). Trans Tech Publications Ltd.

Chepng’etich, E., Bett, E. K., Nyamwaro, S. O., & Kizito, K. (2014). Analysis of technical efficiency of sorghum production in lower eastern Kenya: a data envelopment analysis (DEA) approach.

Chilipunde, R. (2010). Constraints and Challenges faced by Small, Medium and Micro- Enterprise Contractors in Malawi.

Chilipunde, R. (2010). Constraints and Challenges faced by Small, Medium and Micro- Enterprise Contractors in Malawi.

Chism, N., & Armstrong, G. (2010). Project delivery strategy: getting it right. KPMG Internatinal, 1-24.

Fapohunda, J. A., & Stephenson, P. (2010). Optimal construction resources utilization: Reflections of site managers’ attributes. Pacific Journal of Science and Technology, 353-365.

Gupta, C., M., & Boyd, L. (2014). Theory of constraints: a theory for operations management. International Journal of Operations & Production Management, 28 (10), 344-450.

Hair, J. F., Anderson, R. E., Babin, B. J., & Black, W. C. (2010). Multivariate data analysis: A global perspective (Vol. 7).

Invensis. (2017, Oct 12). Estimate Activity Resources in Project Management. Retrieved from https://www.invensislearning.com/resources/pmp/estimate-activity-resources

Kanda, E., Muchelule, Y., & Mamadi, S. (2016). Factors Influencing Completion of Water Projects in Kakamega County, Kenya.

Kenya National Bureau of Statistics. (2012). Kenya Facts and Figures. Nairobi: KNBS.

Locke, E. A., & Latham, G. P. (1990). A theory of goal setting and task performance. Englewood Cliffs, NJ: Prentice-Hall.

Macharia, K. (2017). Agony as delays, heavy traffic mar construction of road projects. Nairobi: Standard Media, 25 April, 2017.

Maina, B. M. (2013). Influence of Stakeholders’ Participation on the Success of the Economic Stimulus Programme: A Case of Education Projects in Nakuru County. Kenya.

Mandala, E. (2018). Influence of Stakeholder’s Involvement in Project Management on The Performance of Road Construction Projects in Kenya: A Case of Bondo Sub County, Siaya County. Siaya County. (Doctoral Disertation, University of Nairobi).

Memon, A. H., Rahman, I. A., Ismail, I., &Zainun, N. Y. (2014). Time Management Practices in Large Construction projects. IEEE Colloquium on Humanities, Science and Engineering, 61-66.

Memon, A. H., Rahman, I. A., Ismail, I., &Zainun, N. Y. (2015). Time Management Practices in Large Construction Project. ResearchGate, 61-65.

Musa, M. H. (2012). Effects of total Quality Management on Performance of Companies in Kenya: A Case of Interbuild Company Limited. Nairobi: Kenya Institute of management.

Nduati, J. K. (2017). Institutional Factors Influencing Completion of Kenya Rural Roads Authority Projects in Ruiru Sub County, Kenya (Doctoral dissertation, University of Nairobi).

Ndungu, P. W. (2008). An analysis on the role of participatory communication in community projects a case of Dagoretti constituency development projects in Nairobi (Doctoral dissertation, University of Nairobi).

Nyamwaro, E. M. (2011). Analysis of Challenges Facing Project Implementation: A Case Study of Ministry of Roads Projects. Nairobi: University of Nairobi.

Oyewobi, L. O., & Ogunsemi, D. R. (2010). Factors Influencing Reworks Occurrence in Construction: A Study of Selected Building Projects in Nigeria. Journal of Building Performance, 1-28.

Project Management Institute (PMI). (2014, July 2). Resource profiling. Retrieved from https://www.pmi.org/learning/library/resource-profiling-macro-view-needs-5945

Rambo, C., Muturi, W., & Ogweno, B. (2016). Determinants of timely completion of road Construction projects financed by Kenya Roads board in Kisumu County. International Joural of Economics, Commerce and Management, 4(11), 360-402.

Vilventhan, A., & Kalidindi, S. N. (2016). Interrelationships of factors causing delays in the relocation of utilities. Engineering, Construction and Architectural Management.

Waihenya, J. W. (2011). Identifying Causes of Cost Overruns in Traditional Contracts in Kenya. Nairobi: University of Nairobi.

Wambugu, D. M. (2013). Determinant of successful completion of rural electrification projects in Kenya: A case study of Rural Electrification Authority. International Journal of Social Sciences and Entrepreneurship, 549-556.

Wambui, D. N. U., Ombui, K., & Kagiri, A. (2015). Factors Affecting Completion of Road Construction Projects in Nairobi City County: Case Study of Kenya Urban Roads Authority (KURA). International Journal of Scientific and Research Publications, 5(11), 2250-3153.

Winch, G. M. (2012). Managing Construction Projects. New York: John Wiley & Sons.

Zikmund, W. G., Carr, J. C., & Griffin, M. (2013). Business Research Methods (Book Only). Cengage Learning.

Downloads

Published

2020-12-16

How to Cite

Mutugi, N. M., & Kyalo, P. D. N. (2020). Influence of Time Management on Implementation of Road Construction Projects in Kilifi County, Kenya. Journal of Entrepreneurship and Project Management, 5(2), 67–92. https://doi.org/10.47941/jepm.497

Issue

Section

Articles